LOCATION
  • Clarksville, IN
SERVICES PROVIDED
  • Excavation
  • Piping
  • Grading
  • Milling
  • Asphalt Paving
  • Striping
DURATION
  • 4 Months

JOB SUMMARY

Installing a new traffic signal at the intersection to improve traffic flow and enhance safety. The project included extensive mass fill, pipe installation, and widening of the roadway with high-quality asphalt to accommodate increased traffic volume and ensure smoother, more efficient movement through the area.

CHALLENGES:

Weather challenges affected the project timeline, but we remained committed to maintaining safety for both our employees and the public throughout every phase. Stringent safety protocols were enforced to ensure a secure environment despite the unpredictable conditions.